2024 and it’s still the electricity, stupid

LEADERSHIP AND ENERGY DEFICIT

2024 and it’s still the electricity, stupid

The latest version of the government's long-term integrated resource plan is visionless and without urgency. It is a ‘plan’ that includes load-shedding for another four years, writes JP LANDMAN.

Image: ANGELA TUCK

OVER the holiday period there were several important developments regarding the major issue facing the country, electricity.

By far the most important was the release of the long-term electricity plan, the Integrated Resource Plan 2023 or IRP 2023. This is a still a draft. After public comments, it will be gazetted to replace IRP 2019. Even as a draft, it is a wholly unsatisfactory document that lets the country down in a crucial area of development. We will discuss this below.

The government also announced three bid windows for 5,000MW of renewable energy, 2,000MW of gas with another one for 1,000MW  in Nelson Mandela Bay to come later in the year, and 615MW of battery storage.

A request for proposals (not a bid window) for 2,500MW of nuclear power is also envisaged for 2024. A nuclear power station takes 10-15 years to develop. This will not make any difference between now and 2030 and we will revert to the issue once the proposals are in and we know what is at stake.

Another important piece of information came from energy analyst Chris Yelland. Based on Eskom data, he calculates that the utility’s energy availability factor (EAF) declined from 58% in 2022 to 54.7% in 2023. This is a stark summary of relentless decline at Eskom and makes a mockery of EAF targets of 65% and 70% set at various stages by management and politicians.


Lees hierdie artikel in Afrikaans:


IRP 2023: visionless and without urgency

The IRP comes to the bleak conclusion that even with new capacity (including 3,000MW gas from Eskom), load-shedding can be expected to continue into 2027. Publishing a “plan" that includes load-shedding for another four years can only be called negligent planning. Common sense dictates that such a plan must set out a path towards plugging the supply deficit and eliminating load-shedding.

The prognosis of load-shedding continuing until 2027 is premised on a realistic EAF of 49%-51%. The only scenario in IRP 2023 where load-shedding is overcome is with an EAF of 66%-69%. Given the trend in Eskom EAF, that is clearly wishful thinking.

Relief from load-shedding can only come from new investments. This is where IRP 2023 really lets the country down.

There is general agreement that South Africa needs 60,000MW of new capacity over 10 years — about 6,000MW per year. The Presidential Climate Commission, for example, recommended 50,000-60,000MW of new renewable capacity over 10 years, plus 3,000-5,000MW of new gas. But for the seven years to 2030, IRP 2023 provides for only 28,000MW to be added, leaving a shortfall of 22,000-32,000MW. For a country in an electricity crisis, this is wholly visionless and without urgency.

Inexplicably, IRP 2023 does not include the 5,000MW renewables from bid window 7 released in December. It also does not include 5,000MW from a future bid window 8, which the minister still has authority to issue. That would cut the deficit by 10,000MW.

IRP 2023 also states that more solar and wind power from the private sector is expected to be connected after 2027 but does not specify any numbers. This week, the National Energy Regulator of SA revealed that in 2023 nearly 4,500MW in new capacity was installed across 392 plants. A log we keep of private projects announced in the media comes to about 11,000MW to be added in the next three to four years. Incomplete as the log may be, you cannot just ignore the private sector contribution.

IRP 2023: renewables, gas and coal

Of the 28,000MW of new capacity over the next seven years which the IRP foresees, 69% will be renewables (wind and solar), 21% gas, 5% dispatchable capacity (essentially storage capacity in whatever technology) and 5% coal.

The 5% for coal refers to the last two units at Kusile and Medupi that will come online during the IRP period. Essentially, there is no new coal. Two 750MW coal plants provided for in IRP 2019, which the minister never activated, do not reappear in IRP 2023. The IRP notes that the Council for Geoscience and World Bank are undertaking a study at a site in Leandra in Mpumalanga to explore clean coal technologies. Should such technologies indeed be developed, coal could feature again in the period after 2030.

Although it is in IRP 2023, I excluded from the 21% gas calculation 1,200MW of gas from Karpowership. The day after the IRP was released, Eskom said it had cancelled the transmission grid capacity reserved for Karpowership and two other providers as they could not reach financial closure for their projects by December 31. Hopefully this is the end of the inappropriate Karpowership deals, even though the IRP draft still includes them.

Another example of reality outstripping the plan is the provision for 3,000MW gas from Eskom. Industry insiders put the cost of that project at R30 billion and more. However, the R254 billion Treasury bailout of Eskom prohibits any further capex apart from essential maintenance. It also prohibits Eskom from taking on further debt. It is unclear how the drafters of IRP 2023 think the Eskom project will materialise.

As the IRP now stands it is already outdated on this 4,200MW of gas. Presumably, that will be fixed in the final draft.

Missed reindustrialisation opportunity

At 69% of new capacity, renewables dominate the bid windows. Sadly, that is not enough.

Quite apart from the fact that 32,000MW more is needed, the miserly allocation for renewables undermines industrial development.

In 2024, for example, IRP 2023 envisions only 1,000MW of solar renewables being installed; in 2026, 1,040MW; and in between, in 2025, there is a spike to 3,000MW. With such a limited and fluctuating uptake, how can industrialisation and localisation of renewable power components take place?

If we play our cards right, green energy can play a huge role in reindustrialising the country. The opportunity is right in front of us, but who will build a factory to produce solar panels or wind components if uptake is going to be so limited and fluctuating? We learnt that lesson when Brian Molefe suspended renewable energy contracts in 2016 and a solar panel factory in KwaZulu-Natal had to close down.

Now what?

There is one big difference between IRP 2019 and IRP 2023, and it is the regulatory context.

The changes announced by President Cyril Ramaphosa in 2021 and 2022 created a liberated electricity market where private players can do their own thing, irrespective of what the minister publishes in an IRP. Over the last two years we have seen private players, from households to big corporates, using this freedom to create their own supply. Traders and energy exchanges are also emerging to buy and sell power, further expanding supply and consumption.

Over the last year, many companies have started embracing renewable power, partly to beat load-shedding but also to move towards being carbon neutral. Anglo American SA, for example, is aiming for 5,000MW of renewable power by 2030 and carbon neutrality by 2040. And 5,000MW is as much as a whole government bid window. Similar stories are unfolding at many other companies.

Even the country’s biggest coal producer, Exxaro, will not invest in more coal assets and is hunting for renewable assets. Earth & Wire, a private sector “utility", has signed agreements to provide many thousands of megawatts to various buyers. The genie has left the bottle.

Reflexivity, the theory that an action carries in it a counteraction, is also at work here. The more IRP 2023 states that load-shedding will continue to 2027 and the more it works with unrealistic gas assumptions, the more people will note the failures and make their own arrangements.

It would be better if there was one national plan that mobilised the public and private sector to play their respective roles to eliminate load-shedding and undertake the long-term development of the energy sector. But IRP 2023 is not that.

So, we will have to rely on private sector initiatives to get us over the line. This is happening.

Transmission capacity

The transmission grid is still a concern but fortunately also a priority in terms of money and attention.

The National Treasury has signed two agreements with European lenders for concessional loans to be used for transmission expansion. The terms of government’s R254 billion bailout of Eskom are creating a bottleneck because of the prohibition on capex programmes mentioned above. That, of course, affects investment in transmission. The new National Transmission Company, for which a new board was announced on January 9, will be fully operational from April 1 and the European money will probably go to that company to proceed with expanding transmission.

Eskom Transmission currently envisions that 1,675km of new lines will be built by 2027 and 12,500km thereafter. The Power Operations & Leadership Association of Southern Africa (Polasa), an industry organisation, has called this a “famine and feast" scenario and argued for some of the projects to be brought forward.

Minister of Electricity Kgosientsho Ramokgopa, who was recently given responsibility for the transmission network, acknowledged the problem in his first news conference of the year. He set a goal of building 6,000km over three years and said he has a mandate to look for private capital to cofinance that.

Economic impact

Due to electricity and logistics constraints, 2024 will again be a tough year economically. No-one expects the economy to expand at the population growth rate of 1.8%. This means 2024 will be the 11th year in which the economy grew more slowly than the population and the country is getting poorer. We already have a decade of declining per capita incomes behind us.

That of course affects unemployment, poverty, the government's ability to collect taxes and having sufficient resources for development. It affects everything. Electricity must be resolved and logistics cleared. Only then can the country again enjoy a rise in per capita incomes.

So what?

  • The further decline in Eskom’s EAF to less than 55% for 2023 underlines the futility of wishing for higher efficiency numbers to deal with load-shedding. It is truly a case of hope triumphing over experience — particularly with power stations that are getting older.
  • The only sustainable way to energy security is massive investment in new capacity. The country needs 50,000-60,000MW of new capacity by 2032. IRP 2023 envisages only 28,000MW and that includes a dubious gas project by Eskom. It leaves a huge supply gap.
  • Fortunately, regulatory reform since 2021 has opened the way for private sector involvement in electricity. Load-shedding, rising tariffs and environmental, social and governance concerns are spurring that involvement. This should help to plug the supply deficit.
  • Getting out of the electricity crisis is a big opportunity for South Africa to stimulate investment, growth and reindustrialisation. IRP 2023 does not seize this opportunity.
  • The Just Energy Transition plan is a much better road map for the country’s evolving energy sector. We will monitor how that is implemented.

♦ VWB ♦


BE PART OF THE CONVERSATION: Go to the bottom of this page to share your opinion. We look forward to hearing from you.

Speech Bubbles

To comment on this article, register (it's fast and free) or log in.

First read Vrye Weekblad's Comment Policy before commenting.